HUAY LA NGAE

PROJECT COST

$147.3 M

AVERAGE ANNUAL ENERGY

289.69 GWh

DAM HEIGHT

1,218 M

CATCHMENT AREA

279.8 Km2

Installed Capacity

60 MW

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam,quis nostrud exercitation ullamco laboris nisi

Project Cost $147.3 M
Shareholder

Chaleun Sekong Energy CO., LTD 30%

Sekong Development CO., LTD 70%

Installed Capacity 60 MW
Energy Generation 289.69 Gwh
Maximum Turbine 12 m³/s
Design net Head 1,215.18 m
Type of turbine Vertical Pelton
Off-taker EVN
Catchment Area 279.8 km²
Rain flow releases 2,800 mm
Inflow Average 123×106 m3/s
Reservoir 14 M m³
Reservoir Surface Area 93.6 km²
Full supply level 1,215 m a.s.l
Min operating level 1,189 m a.s.l
Main Dam
Type RCC
Height 58 m
Crest Length 182 m
Crest level 782.5 m a.s.l
Water flow channels
Type Inverted U-shaped section
Length 3,990 m
Hills of channels  
Open Channels 2.5 m
convert block 2.5 m

Penstock

Type Steel Lined Tunnel
No of pipe 1
Internal diameter 2 m
Length 2,787.7 m
 
Spillway
Type WES practical weir
No of gate 3
Design Flood Discharge 701 m³/s
Headrace Tunnel
Type Inverted U-shaped section
Flow rate 3.91 %
Internal diameter 2.8m x 3.5m
Length 3,918 m

Station 230 kW GIS (EGAT) / 115 kW

AIS (Electricite du Laos)

Height 586
Ground size 54m x 25m
Powerhouse
Installed Capacity 60 MW
Number of Unit 2
Turbine Type SF30-10/3300
Max Powerhouse Discharge 5.744 m³/s
Superstructure dimensions 581.7 m a.s.l
230KV Transmission Line
Substation Nam E-Moun
Length 41 Km
Circuit Type 1
Conductor Size ACSR 300
 

Legal Documents

  1. On 21/07/2015 Signed a Memorandum of Understanding (MOU)   
  2. On 17/02/2015Project Development Agreement (PDA) was signed
  3. On 14/09/2017The Feasibility study of the project was approved
  4. On 22/11/2016 Completed the report of Environmental and Social Impact Assessment (ESIA)
  5. On 22/11/2016Completed the Environmental and Social Management and Monitoring Plans (ESMMP)
  6. On 01/02/2021 Completed the Environmental and Social Management and Monitoring Plans-construction Phase (ESMMP-CP)
  7. On 14/08/2020 Complete basic design certification issued
  8. On 07/09/2020Completed the investment license
  9. On 30/09/2020Completed the enterprise registration
  10. On 11/11/2020Completed the ratification of the annex to the concession agreement with environmental, social and natural obligations (Annex C-CA)
  11. On 15/01/2019Completion of Environmental Certificate for Renewal of Social and Natural Environmental Management and Monitoring Plan (ESMMP)
  12. On 24/11/2021 Completed the environmental minimum water flow certificate
  13. On 07/05/2021 Completed the environmental certificate for the transmission corridor
  14. On 22/12/2021 Signed a concession agreement with the Government of the Lao PDR

 

  1. EPC contractor: POWERCHINA Sinohydro Bureau 10., Ltd

  2. OE: China Northwest Water Resources and Hydropower Construction Engineering Consulting CO., LTD

 

 

  1. On 21/07/2015 Signed a Memorandum of Understanding (MOU)   
  2. On 17/02/2015Project Development Agreement (PDA) was signed
  3. On 14/09/2017The Feasibility study of the project was approved
  4. On 22/11/2016 Completed the report of Environmental and Social Impact Assessment (ESIA)
  5. On 22/11/2016Completed the Environmental and Social Management and Monitoring Plans (ESMMP)
  6. On 01/02/2021 Completed the Environmental and Social Management and Monitoring Plans-construction Phase (ESMMP-CP)
  7. On 14/08/2020 Complete basic design certification issued
  8. On 07/09/2020Completed the investment license
  9. On 30/09/2020Completed the enterprise registration
  10. On 11/11/2020Completed the ratification of the annex to the concession agreement with environmental, social and natural obligations (Annex C-CA)
  11. On 15/01/2019Completion of Environmental Certificate for Renewal of Social and Natural Environmental Management and Monitoring Plan (ESMMP)
  12. On 24/11/2021 Completed the environmental minimum water flow certificate
  13. On 07/05/2021 Completed the environmental certificate for the transmission corridor
  14. On 22/12/2021 Signed a concession agreement with the Government of the Lao PDR
  15. On 01/04/2023 First Impounding 

 

Project progress

Start Construction Phase:

  • Model and Powerhouse

  • Survey the area

  • Paving the road

  • Building the tunnel

10%

Construction start phase

  • Model and Powerhouse

  • Survey the area

  • Paving the road

  • Building the tunnel

39.72%

Construction in 2022:

  • Main Dam
  • Diversion dam
  • Diversion Tunnel
  • Water Supplement Tunnel
  • Sur shaft
  • Penstock
  • Powerhouse
  • Mechanical and electrical equipment installation
  • Transmission line construction
  • Auxiliary projects

70%

Construction in early 2023:

  • Powerhouse

  • Main Dam

  • Tunnel

  • Water Supply Tunnel

  • Pen Stock

  • Surge Tank

  • Saddle Dam

  • Transmission Line

89.92%

Construction in mid 2023:

  • Powerhouse
  • Main Dam
  • Penstock
  • Surge Tank
  • Saddle Dam

98.9%