PROJECT COST
$142.527 M
AVERAGE ANNUAL ENERGY
288 GWh
DAM HEIGHT
50 M
CATCHMENT AREA
861 Km2
Installed capacity
66 MW
Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam,quis nostrud exercitation ullamco laboris nisi
- ORGANIZATION CHART
- GENERAL INFORMATION
- TECHNICAL STRUCTURE
- HYDRO-ELECTRO-MECHANICAL INFORMATION
- Legislative Document
- Total recipients and sub-recipients
- Important steps of the project
Project Cost | $142.527 Million |
Shareholder | CSE 100% |
Installed capacity | 66 MW |
Annual energy average | 288 GWh |
Max power generator | 76.20 m³/s |
The water level | 98.8 m |
Type of Turbine | Francis 3 Unit |
Offer taker | EVN |
Catchment Area | 200.8 Km2 |
Annual Average Rain Fall | 2,315 mm |
Annual Average Discharge | 36.6 m³/s |
Reservoir Storage Capacity | 71.4 Million m³ |
Reservoir Storage Capacity | 4.2 Km2 |
Full Supply Level | 427 m a.s.l |
Min Operating level | 420 m a.s.l |
Main Dam | |
Type | Gravity Concrete |
Height | 65 m |
Crest Length | 280 m |
Headrace Canal | |
Type | Exposed Excavation |
Length | 114 m |
Longitudinal Gradient | 0.001% |
Penstock | |
Type | Steel Liner |
Number of Pipe | 1 |
Diameter | 4.2 m |
Length | 370 m |
Spillway | |
Type | Sluice Gate |
Number of Gate | 4 |
Design Flood Discharge p=0,1% | 3,780 m³/s |
Headrace Tunnel | |
Type | Reinforced Concrete |
Design Discharge | 76.2 m³/s |
Diameter | 5.4 – 4.2 m |
Length | 1,430 m |
Tailrace Canal | |
Type | Open Canal |
Length | 205 m |
Switchyard 115 kV | |
Elevation | 354.5 m a.s.l |
Dimension | 55m X 40m |
Powerhouse | |
Installed Capacity | 66 MW |
Number of Units | 3 Unit |
Turbine Type | Vertical Francis |
Max Powerhouse Discharge | 76.2 m³/s |
Erection Floor Elevation | 324.5 m a.s.l |
115 KV Transmission Line | |
Substation | Sapaothong Substation |
Length | 36 Km |
Circuit Type | Single Circuit |
Conductor Size | 240 mm2 |
Legislative Document
- On 19/1/2010 Memorandum of Understanding (MOU)
- In 2010 Project Development Agreement (PDA)
- On 31/1/2013 Concession Agreement (CA)
- On 3/4/2011 Power Purchase Agreement (PPA)
- On 11/2011, construction started
- On 06/2018, the construction was completed
- On 20/7/2018 Commercial operation date (COD)
Main Contractor
Main Contractor: Hoang Anh Gia Lai Hydropower Joint Stock Company.
- All of Construction structural work items (Civil Work);
- Electrical system.
- Mechanical systems.
- High voltage transmission line 22 kWh.
- 115 kWh.
Designers and supervisors
- Construction design (Basic design): East Asia Investment and Construction Consultant JSC.
- Construction Supervision (Owner Engineer & Construction Supervision): East Asia Investment and Construction Consultant JSC.
Repair contractor
- Construction Supervision (Owner Engineer & Construction Supervision) ILF Consulting Engineers:
- Headrace Tunnel, (Grouting) (Slope Protection), (Civil work) (Bottom Outlet): Right Tunnelling Co., Ltd.
- (Bottom Outlet) Whessoe Lao Sole Co., Ltd.:
- Procurement of dam measuring equipment (Dam Instrument) Nari Group Corporation
- Installation of dam measuring equipment (Dam Instrument) Siam Tone Co., Ltd.:
- Checking, repairing and testing the engine. Asia Motor Service Center Co., Ltd.: (Mechanical Work and Commissioning).
- Inspection and repair of electrical systems in Powerhouses, inspection and repair work (Switchyard): Tonnam Energy Part., Ltd.
Important steps of the project
- On 31-January-2013, the Nam Kong 2 Hydropower Project has a concession agreement with the Government of the Lao PDR;
- The original developer was Hong Anh Attapeu Electric Company Limited;
- In 2011, construction of the Nam Kong 2 hydropower project began;
- In 2016, Chaluen Sekong Power Company became a 100% shareholder from Hong Anh Attapeu Electric Co., Ltd. and continued to build 10% of the unfinished work until it was completed;
- In June 2018 completed construction;
- In June 2018 Experiment with electricity generation
- On July 20, 2018 Commercial operation date (COD)