NAM NGIEP 3A

Project Cost

$102 M

Annual energy average

144 GWh

Height DAM

30 M

drainage area

336 Km2

Installed capacity

44 MW

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam,quis nostrud exercitation ullamco laboris nisi

Project Cost $102 Million
Shareholder CSE 100%
Installed capacity 44 MW
Annual energy average 144 GWh
Max power generator 36.70 m³/s
The water level 150 m
Type of Turbine Vertical Francis 5 Unit
Offer taker EDL
Catchment Area 336 Km2
Annual Average Rain Fall 1,320 mm
Mean Annual precipitation  36.6 m³/s
Reservoir Storage Capacity 13.85 Million m³
Reservoir Storage area 1.8 Km2
Full Supply Level 1,050 m a.s.l
Min Operating level 1,048 m a.s.l
Main Dam
Type Earth till Dam
Height 30 m
Crest Length 110 m
Headrace Canal
Type Open Canal & Box culvert
Length 1,100 m
Open Canal 600 m
Box culvert 500 m
Canal slope
Penstock
Type Steel Liner
Number of Pipe 1
Diameter 3.00 m
Length 450 m
Spillway
Type Steel Sluice Gate
Number of Gate 2
Maximum Discharge 450 m³/s
Switchyard 115 kV
Elevation 904.60 m a.s.l
Dimension 45m X 54m
Powerhouse
Installed Capacity 44 MW
Number of Unit 5 Unit
Turbine Type

Vertical Francis 3 & horizontal Francis 2

Max Powerhouse Discharge 34 m³/s
Erection Floor Elevation 901.60 m a.s.l
115 KV Transmission Line
Substation NAHO
Length 3 Km
Number of circuits 1
Conductor Size 240 mm2

Legislative Document

  1. The last version of FS was approved in June 2010.
  2. Received environmental certification on April 20, 2012.
  3. The Nam Ngeip 3A Hydropower Project has a concession agreement with the Government of the Lao PDR on 28 November 2013.
  4. On April 26, 2013, Nam Ngiep 3A was signed a power purchase agreement with EDL.
  5. Signed a land lease agreement on 5 July 2013.

Total recipients and sub-recipients

Main structural work and additional construction work

  • Main Structural Work: Construction of earth fill dam, canals, overflow drainage buildings, Bottom outlet, waterworks, water pipelines, power plants, purchase and installation of electrical and mechanical systems, switchyard and 115 KV transmission lines.
  • Additional work: Monitoring and consulting in construction, design, document inspection, material testing, construction drawing (Shop drawing), quality inspection and accuracy of work

Construction contractor

  • Phongsubthavy Bridge-Road Construction Company Limited: Detailed design: Construction of earth fill dam, Bottom outlet, canals, Spillway and Intake.
  • Construction control (Supervise construction) TUGBOAT TEAM COMPANY LIMITED.
  • Construction of Penstock, Spillway and Bottom Outlet: T-RAX Steel Co., Ltd.
  • Construction of 115 kw transmission line and Structural work of Switchyard: Tonnam Energy Ltd., Part.
  • Construction of Powerhouse: R.L. Corporation Co., Ltd.
  • Supply and installation of electrical and mechanical systems in Powerhouses. Supply and installation of electrical and mechanical systems in Switchyard: Dongfang Electric International Corporation

Important steps of the project

  1. The last version of FS was approved in June 2010.
  2. Received environmental certification on April 20, 2012.
  3. On April 26, 2013, Nam Ngiep 3A was signed a power purchase agreement with EDL.
  4. Signed a land lease agreement on 5 July 2013.
  5. The Nam Ngeip 3A Hydropower Project has a concession agreement with the Government of the Lao PDR on 28 November 2013.
  6. The construction of the Nam Ngiep 3A hydropower project began in September 2011.
  7. Testing the generate electricity in August 2014.
  8. Completed the construction in September 2014.
  9. After the Official Commercial operation of electricity, Phongsubthavy Bridge-Road Construction Co., Ltd. has been generating electricity for export to Electricite du Laos for 13 months.
  10. As of 7/8/2015, Phongsubthavy Bridge-Road Construction Company sold the dam to TK Group Co., Ltd.
  11. As of 15/03/2016, Chaleun sekong Power Co., Ltd. has become a 100% shareholder after TK Group Co., Ltd. And has been selling electricity until now.
  12. Concession age total 27 years after COD.
  13. Official Commercial of electricity COD on February 2015; (Unit 4,5 October 1, 2014)

Contact Us

CSE Building, Nongbon Road, Unit 8, Nongbon Village, Xaysettha District Vientiane, Lao PDR.

+856 (0) 21 417788 or 417789
headoffice@csenergy.la