HUAY LA NGAE

PROJECT COST

$147 M

AVERAGE ANNUAL ENERGY

289.69 GWh

DAM HEIGHT

1,218 M

CATCHMENT AREA

279.8 Km2

Installed Capacity

60 MW

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam,quis nostrud exercitation ullamco laboris nisi

In Progress

Project Cost $147 M
Shareholder CSE 30%
Installed Capacity 60 MW
Energy Generation 289.69 Gwh
Maximum Turbine 12 m³/s
Design net Head 1,215.18 m
Type of turbine Vertical Francis x 5 Units
Off-taker EVN
Catchment Area 279.8 km²
Rain flow releases 2,800 mm
Inflow Average 123×106 m3/s
Reservoir 14 M m³
Reservoir Surface Area 93.6 km²
Full supply level 1,215 m a.s.l
Min operating level 1,189 m a.s.l
Main Dam
Type Plain Cement Concrete
Height 58 m
Crest Length 178.86 m
Crest level 782.5 m a.s.l
Water flow channels
Type Inverted U-shaped section
Length 3,990 m
Hills of channels  
Open Channels 2.5 m
convert block 2.5 m

Penstock

Type Steel Lined Tunnel
No of pipe 1
Internal diameter 2 m
Length 2,787.7 m
 
Spillway
Type WES practical weir
No of gate 3
Design Flood Discharge 701 m³/s
Headrace Tunnel
Type Inverted U-shaped section
Flow rate 3.91 %
Internal diameter 2.8m x 3.5m
Length 3,918 m

Station 230 kW GIS (EGAT) / 115 kW

AIS (Electricite du Laos)

Height 586
Ground size 54m x 25m
Powerhouse
Type  
Installed Capacity 60 ເມກາວັດ
Number of Unit
2
Turbine Type
SF30-10/3300
Max Powerhouse Discharge
5.744 ມ³/ວິນາທີ
Height 581.7 M A.S.L
 230 KV Transmission Line EDL
Substation Nam E-moun
Length 41 ກມ
Circuit Type 1
Conductor Size ACSR 300

Legal Documents

  1. On 21/07/2015 Signed a Memorandum of Understanding (MOU)   
  2. On 17/02/2015Project Development Agreement (PDA) was signed
  3. On 14/09/2017The Feasibility study of the project was approved
  4. On 22/11/2016 Completed the report of Environmental and Social Impact Assessment (ESIA)
  5. On 22/11/2016Completed the Environmental and Social Management and Monitoring Plans (ESMMP)
  6. on 01/02/2021 Completed the Environmental and Social Management and Monitoring Plans-construction Phase (ESMMP-CP)
  7. 0n 14/08/2020 Complete basic design certification issued
  8. On 07/09/2020Completed the investment license
  9. On 30/09/2020Completed the enterprise registration
  10. On 11/11/2020Completed the ratification of the annex to the concession agreement with environmental, social and natural obligations (Annex C-CA)

. on 15/01/2019Completion of Environmental Certificate for Renewal of Social and Natural Environmental Management and Monitoring Plan (ESMMP)

  1. on 24/11/2021 Completed the environmental minimum water flow certificate
  2. on 07/05/2021 Completed the environmental certificate for the transmission corridor
  3. on 22/12/2021 Signed a concession agreement with the Government of the Lao PDR

 

  • EPC contractor    POWERCHINA Sinohydro Bureau 10., Ltd

  • In Progress

Important step of the project:

  1. On 21/07/2015Signed a Memorandum of Understanding (MOU)
  2. On 17/02/2017 Project Development Agreement (PDA) was signed
  3. On 22/12/2021 Signed a concession agreement with the Government of the Lao PDR

Project progress

Construction start phase:

  • Model and Powerhouse

  • Survey the area

  • Paving the road

  • Building the tunnel

80,46%

Construction start phase

  • Model and Powerhouse

  • Survey the area

  • Paving the road

  • Building the tunnel

39.72%

Construction start overall 2022 to early 2023

  • Main Dam
  • Diversion dam
  • Diversion Tunnel
  • Water Supplement Tunnel
  • Sur shaft
  • Penstock
  • Powerhouse
  • Mechanical and electrical equipment installation
  • Transmission line construction
  • Auxiliary projects

80%