Project Cost
$ 334,113,032
Annual energy average
586 GWh
Height DAM
997.6 M
Installation capacity
128 MW 2
Installation capacity
128 MW
Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam,quis nostrud exercitation ullamco laboris nisi
- ORGANIZATION CHART
- GENERAL INFORMATION
- TECHNICAL STRUCTURE
- ELECTRICAL-MECHANICAL INFORMATION
- LEGISLATIVE DOCUMENTS
- CONTRACTOR
- PROJECT MILESTONES
No Data
Project Costs |
334,113,032 US Dollar |
Shareholder |
CSE, Kobe and EDL |
Installation capacity |
128 MW |
Annual Energy Average |
586 GWh |
Annual Average Discharge |
20.8 m3/s |
Height |
653.1 M |
Type of Turbine |
2 Pelton and 1 Francis |
OFF-TAKER |
EDL Sent Through Electricite Du Cambodge (EDC) |
Catchment Area |
142.4 km2 |
Annual Average Rain Fall |
3,600 mm (Information between 1992-2015) |
Annual Average Outflow |
17.64 m3/s |
Reservoir |
6.05 km2 (NAM PA and NAM PHAK) 2,80 km2 (NAM PA) Total 8,85 km2 |
Maximum water reservoir level (MWRL) |
885 h |
Maximum Operating Level |
FSL EL= 993.00 m asl (NAM PA) FSL EL= 909.00 m asl (PHOU PONG) |
Minimum Operating Level |
MOL EL= 955 m asl (NAM PA) MOL EL= 905 m asl (PHOU PONG) |
test | test |
test | test |
test | test |
test | test |
Main Dam NAM PA |
|
Type |
Rock fill dam (AT PHAO) |
Height |
77.6 M |
Crest Level |
997.6 M |
Crest Level |
997.6 M |
Hight water level |
995,6 M |
Low water level |
955 M |
Spillway |
|
Type |
Concrete U Drain Block |
diameter of the gate |
N/A |
The space between the gate and dam ridge |
N/A |
Flood Gate |
1000 years |
Water flow rate |
392 m3/s |
High pressure inline water pipe |
|
Type |
Steel pipe |
inside diameter |
2.5 M |
Length |
1,859 M |
Hills |
33% |
Tunnel |
|
Type |
Concrete |
Length |
2,847 M |
inside diameter |
3 ມ |
Hills |
1.76% |
Water Intake |
|
Low water level |
MOL EL= 905 m asl (Phou Pong) |
Ground-level water |
EL= 898 M |
Ground-level water intake |
EL= 899 M |
Open Gate |
Gate Gantry Crain |
Switchyard |
|
Type |
Air insulate Switchgear (AIS) |
High voltage |
115 kW |
Powerhouse |
|
Type |
Powerhouse on the floor |
Number of turbines |
2 Units |
Number of generators |
2 Machine |
Installation capacity |
120 MW |
Net height |
653.1 M |
Effective height |
670.8 M |
Outflow |
|
Channel Flow |
Open Channel Concrete |
Groundwater levels |
EL= 229,5 M |
Surface Water |
EL= 232.2 M |
transmission line kW |
|
Type |
Structure |
High Voltage |
115 kW |
Length |
22 Km |
- On December 09, 2020 Ministry of Energy and Mines issues license to Chaluen Sekong Energy Co., Ltd. to start construction of the project NamPhak
Project Owner: Chaluen Sekong Energy Co., Ltd.
– Basic Design: Tractebel Engineering Ltd.
– Consultant: Tractebel Engineering Ltd.
– Geological survey SSSDC, BMEC
- Initial survey: 2007, by KOBE Company (KGPC)
- Initial project owner: KOBE Company (KGPC)
- feasibility study (FS): Built in 2010, by (AECOM)
- Consultant AECOM: Design to Run Off, By:
1) Machine 8 MW + 100 MW,
2) Machine 8 MW + 150 MW,
3) Machine 8 MW + 120 MW
- Updated feasibility study (FS): 2014-2015 by: LAO MAJOR INDIA.
- Transfer Project Ownership: 2017, Chaluen Sekong Energy Co., Ltd.
- Updated feasibility study (FS): 2017-2020 by POYRY / AFRY Consultants
- Start building infrastructure: 2021 By Chaluen Sekong Energy Co., Ltd.
Project milestones
The pioneering phase and construction begins in 2021:
-
Main Dam Model, Powerhouse, and Site offices
-
Locals Survey, and the Roads
-
Compensate for coffee plantation damage to people in the project area.
-
Clear the area, and started build the Roads of the PARKSONG side, first and the second phase.
-
Install, and build power lines of 22 kW.
-
Build the Bridge to Cross NamPhak
-
Clear the area, and start building camps and Site offices.
The Overall constructions phase in 2022:
Infrastructure construction work phase 1
Build the road inside the dam to the tunnel Phase 2
Build the road R7-R8 PATHUMPHONE Side
Build grid systems 22 kW from the power station to the camp.
Building camps, and field offices
The Overall constructions phase in early 2023:
Camp CSE
Camp SD5
Nam Pa Dam
Nam Phak Dam
Phou Pong Dam
Powerhouse 8MV
Powerhouse 160MV
Penstock
The Overall constructions phase in March 2023:
- Road R1-R2
- Asphalt mixing plant
- Zigzag road to powerhouse 160 MW
- Guard house SD5 asset road R3-R4 and R5-R6
- Mixing concrete plant No.2
- Transmission line 22 KV on north road