PROJECT COST

$102 M

AVERAGE ANNUAL ENERGY

144 GWh

DAM HEIGHT

30 M

CATCHMENT AREA

336 Km2

Installed Capacity

44 MW

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam,quis nostrud exercitation ullamco laboris nisi

ORGANIZATION CHART

Empty section. Edit page to add content here.

GENERAL INFORMATION

Project Cost $102 M
Shareholder CSE 100%
Installed Capacity 44 MW
Average Annual Energy 144 GWh
Design 36.70 m3/s
Rated Head 153 m
Turbine Type – Vertical Francis 3 Units

– Horizontal Francis 2 Units

Offtaker EDL
Catchment Area 336 Km2
 Mean Annual precipitation 14m3/s
Mean Annual runoff 2400 mm
Reservoir Storage volume 13.85 Million m3
Maximum Reservoir Surface Area 1.8 Km2
Full Supply Level 1,050 m a.s.l
Minimum Operating Level 1,048 m a.s.l

TECHNICAL STRUCTURE

Main Dam
Type Earth till Dam
Height 30 m
Crest Length 110 m
Headrace Channel
Type Open Channel & Box culvert
operation Chanel 1,100 m
Longitudinal Gradient 500 m
Penstock
Type Steel pipe
Number of cell 1
Diameter 3.00 m
Length 450
Longitudinal Gradient
Spillway
Type Steel Sluice Gate
Number of Gate 2
Maximum  Discharge 450 m3/s
Headrace Tunnel(none)
Type  –
Design Discharge  –
Diameter  –
Length  –
Tailrace Channel (none)
Type  –
Length  –
Switchyard 115kV
Elevation 904.60 m a.s.l
Dimension 45m x 54m

HYDRO-ELECTRO-MECHANICAL INFORMATION

Powerhouse
Installed Capacity 44 MW
Number of Units 5
Turbine Type Vertical Francis 3 & horizontal Francis 2
Max Discharge 34 m3/s
Erection Floor Elevation 901.60 m a.s.l
115KV Transmission Line
Substation NAHO
Length 3 Km
Number of circuit 1
Conductor Size 240 mm2

PROJECT TIMELINE

RELATED PROJECT

NAM KONG 2

NAM NGIEP 3A

Contact Us

CSE Building, Nongbon Road, Unit 8, Nongbon Village, Xaysettha District Vientiane, Lao PDR.

+856 (0) 21 417788 or 417789
headoffice@csenergy.la