Installed Capacity

  • 60 MW

Huay La Ngae Power Plant is located in Bo Ping Village, Kaluem District, Xekong Province, which has an installed capacity of 60 MW.

PROJECT COST

$147.3 M

AVERAGE ANNUAL ENERGY

289.69 GWh

DAM HEIGHT

1,218 M

CATCHMENT AREA

279.8 KM2

Project milestones

  • Main Dam 100% 100%
  • Diversion Dam 100% 100%
  • Penstock 100% 100%
  • Surge Shaft 100% 100%
  • Powerhouse 100% 100%
  • Transmission Line 92.30% 92.30%
  • Camp (office and staff accommodation) 100% 100%

98.9% (September 2024)