NAM THEUN 1

PROJECT COST

$1,335 M

AVERAGE ANNUAL ENERGY

2,638.1 GWh

DAM HEIGHT

177 M

CATCHMENT AREA

13,856 Km2

Installed Capacity

650 MW

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam,quis nostrud exercitation ullamco laboris nisi

Project Cost $1,335 Million
Shareholder PSG 32%, CSE 28%, EGCO 25%, EDL-GEN 15%
Installed Capacity 650 MW
Average Annual Energy 2,638.1 GWh
Maximum Turbine Discharge 513.7 m³/s
Rated Head 297 m
Turbine Type Vertical Axis Francis
Offertaker EGAT / EDL
Catchment Area 13,856 Km²
Annual Average Rain Fall 2,496 mm
Annual Average Discharge 320 m³/s
Reservoir Storage Capacity 3,009 Million m³
Reservoir Surface Area 93.6 Km²
Full Supply Level 292 m a.s.l
Minimum Operating Level 250 m a.s.l
Main Dam
Type RCC (Curved Gravity Dam)
height 177 m
Crest width 8 m
Crest level 297 m a.s.l + 0.75 m high parapet wall
River Diversion
Type Single Tunnel and Overtopping Cofferdams
Length 932 m
Tunnel Diameter 11 m
   
Penstock
Type Embedded (Pressure Tunnel)
Number of Pipe 1
Diameter 10 m / 8.95 m / 6.30 m / 4.50 m
Length 565 m (EDL) / 544 m (EGAT)
Spillway
Type Radial Gate
Number of gates 6
Design Flood Discharge 25,500 m³/s
Max. inflow peak 30,200 m³/s
Switchyard 230 kV GIS (EGAT)/115 kV AIS (EDL)
Height 586 m
Ground size  54 m x 25 m
Powerhouse
Type Pit Powerhouse, 2 pits
Installed Capacity 650 MW
Number of Unit 3
Turbine Type Vertical Axis Francis
Max Powerhouse Discharge 513.7 m³/s
Superstructure dimensions 25.8 m x 91.10 mx14.8 (WxLxH)
115KV Transmission Line EDL
Substation Pakxan-Khonsong
Length 7.5 Km
Circuit Type 7.5 Km Double Circuit; 1.5 Km Single Circuit
Conductor Size 795 MCM
500KV Transmission Line EGAT
Substation Nabong
Length 154 Km
Circuit Type ACSR/GA
Conductor Size 795 MCM

Project legislative documents

  1. On March 09, 2012 Signed a Memorandum of Understanding (MOU) with the Government of the Lao PDR
  2. Project Development Agreement (PDA) was signed on September 09, 2014
  3. Completed the report of Environmental and Social Impact Assessment (ESIA) on September 16,2014
  4. Completed the Environmental and Social Management and Monitoring Plans (ESMMP) On September 16, 2014
  5. The Feasibility study of the project was approved on February 22, 2016
  6. Signed a concession agreement (CA) with the Government of the Lao PDR on June 14, 2016
  7. On September 23, 2017, a power purchase agreement was signed with the Electricity Generating Authority of Thailand (EGAT).
  8. Completed the Environmental and Social Management and Monitoring Plans-construction Phase (ESMMP-CP) on June 19, 2018.

Total recipients and sub-recipients

In Progress

Construction contractor

In Progress

Important steps of the project

  1. On March 09, 2012 Signed a Memorandum of Understanding (MOU) with the Government of the Lao PDR
  2. Project Development Agreement (PDA) was signed on September 09, 2014
  3. Completed the report of Environmental and Social Impact Assessment (ESIA) on September 16,2014
  4. Completed the Environmental and Social Management and Monitoring Plans (ESMMP) On September 16, 2014
  5. The Feasibility study of the project was approved on February 22, 2016
  6. Signed a concession agreement (CA) with the Government of the Lao PDR on June 14, 2016
  7. On September 23, 2017, a power purchase agreement was signed with the Electricity Generating Authority of Thailand (EGAT).
  8. Completed the Environmental and Social Management and Monitoring Plans-construction Phase (ESMMP-CP) on June 19, 2018.
  9. Official Commercial of electricity COD on 12 August 2022.

Project milestones

Main components of dams:

    • Main dam
    • Water intake
    • Headrace tunnel
    • Powerhouse
    • Switch yard
    • Transmission line system

10%

Main components of dams:

    • Main dam
    • Water intake
    • Headrace tunnel
    • Powerhouse
    • Switch yard
    • Transmission line system

30%

Main components of dams:

    • Main dam
    • Water intake
    • Headrace tunnel
    • Powerhouse
    • Switch yard
    • Transmission line system

50%

Main components of dams:

    • Main dam
    • Water intake
    • Headrace tunnel
    • Powerhouse
    • Switch yard
    • Transmission line system

70%

Main components of dams:

    • Main dam
    • Water intake
    • Headrace tunnel
    • Powerhouse
    • Switch yard
    • Transmission line system

90%

Main components of dams 100%:

    • Main dam
    • Water intake
    • Headrace tunnel
    • Powerhouse
    • Switch yard
    • Transmission line system

100%