NAM PHAK

Project Cost

$ 420 M

Annual energy average

788 GWh

Height DAM

Nam Phak Dam 26,6 m

Nam Pa Dam 79,6 m

Pou Pong 76,5 m

Installation capacity

128 KW2

Installation capacity

168 MW

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam,quis nostrud exercitation ullamco laboris nisi

No Data

Project Costs $420 M
Shareholder CSE 80%, EDL 15%, KOBE 5%
Installation Capacity 168 MW
Annual Energy Average 586 GWh
Annual Average Discharge 21 m3/s
Height 652.1 m
Type of turbine
Off-Taker EDL Sent Through Electricite Du Cambodge (EDC)
Catchment Area 134,51 KM2
Annual Average Rain Fall 4,900 mm
Annual Average Outflow 13 m3/s
Reservoir 168 Millions m3
Maximum Water Resistance Level (MWRL) 10,6 KM2
Full Supply Level 993 m a.s.l
Min Operating level 955 m a.s.l
Main Dam Nam Pa
Type
Height 28 m
Crest Level 250 m
Headrace Canal
Type
Length
Inside Diameter
Penstock
Type
Number of Pipe
Diameter
Length
Inside Diameter
  Spillway

Type
Number of Gate
Max Inflow peak
Design Flood Discharge
 Dam
Type
Number of Gate
Headrace Tunnel
Type
Design Discharge
Diameter
Length
Tailrace Canals
Type
Length
Switchyard 115kV
Elevation
Dimension
Powerhouse
Installed Capacity 168 MW
Number of Unit 2
Turbine Type

Max Powerhouse Discharge 26 m³/s
Erection Floor Elevation
115 KV Transmission Line
Substation
Length
Number of circuits
Conductor Size

  1. On December 09, 2020 Ministry of Energy and Mines issues license to Chaluen Sekong Energy Co., Ltd. to start construction of the project NamPhak

Project Owner:                                  Chaluen Sekong Energy Co., Ltd.

–   Basic Design:                               Tractebel Engineering Ltd.

–   Consultant:                                  Tractebel Engineering Ltd.

–   Geological survey                         SSSDC, BMEC

  • Initial survey:                                              2007, by KOBE Company (KGPC)
  • Initial project owner:                            KOBE Company (KGPC)
  • feasibility study (FS):                              Built in 2010, by (AECOM)
  • Consultant AECOM:                                    Design to Run Off, By:

         1) Machine 8 MW + 100 MW,

            2) Machine 8 MW + 150 MW,

            3) Machine 8 MW + 160 MW

  • Updated feasibility study (FS):              2014-2015 by: LAO MAJOR INDIA.
  • Transfer Project Ownership:                  2017, Chaluen Sekong Energy Co., Ltd.
  • Updated feasibility study (FS):                             2017-2020 by POYRY / AFRY Consultants
  • Start building infrastructure:                                2021 By Chaluen Sekong Energy Co., Ltd.

Project milestones

The pioneering phase and construction begins in 2021: 

  • Main Dam Model, Powerhouse, and Site offices

  • Locals Survey, and the Roads

  • Compensate for coffee plantation damage to people in the project area.

  • Clear the area, and started build the Roads of the PARKSONG side, first and the second phase.

  • Install, and build power lines of 22 kW.

  • Build the Bridge to Cross NamPhak

  • Clear the area, and start building camps and Site offices.

1%

The Overall constructions phase in 2022:

  • Infrastructure construction work phase 1

  • Build the road inside the dam to the tunnel Phase 2

  • Build the road R7-R8 PATHUMPHONE Side

  • Build grid systems 22 kW from the power station to the camp.

  • Building camps, and field offices


4,20%

The Overall constructions phase in early 2023: 

  • Camp CSE

  • Camp SD5

  • Nam Pa Dam

  • Nam Phak Dam

  • Phou Pong Dam

  • Powerhouse 8MV

  • Powerhouse 160MV

  • Penstock

8,7%

The Overall constructions phase in March 2023:

  • Road R1-R2
  • Asphalt mixing plant
  • Zigzag road to powerhouse 160 MW
  • Guard house SD5 asset road R3-R4 and R5-R6
  • Mixing concrete plant No.2
  • Transmission line 22 KV on north road

10,51%

The Overall constructions phase in 2023 (Q2): 

  • Cushing Plant

  • Nam Pa Dam (Excavation)

  • NAM PA Tunnel (Excavation and Support)

  • Excavation of Nam Pa Still basin Portal

  • Phou Pong Dam (Excavation)

  • Phou Pong Tunnel

  • Nam Phak Tunnel

  • Power House 160 MW (Excavation)

  • North Diversion Tunnel

19,75%

The Overall constructions phase in end of year 2023:

  • NamPha Power House 8MW (Excavation)
  • Excavation of NamPha still basin portal
  • Excavation of Penstock foundation
  • NamPhak Dam pre-work.
  • Facilities for EM work

25,06%

Contact Us

CSE Building, Nongbon Road, Unit 8, Nongbon Village, Xaysettha District Vientiane, Lao PDR.

+856 (0) 21 417788 or 417789
headoffice@csenergy.la