XE NAM NOY 1

PROJECT COST

$36.86M

AVERAGE ANNUAL ENERGY

80 GWh

DAM HEIGHT

7 M

CATCHMENT AREA

1,284 Km2

Installed Capacity

14.8 MW

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam,quis nostrud exercitation ullamco laboris nisi

Project Cost $36.86 M
Shareholder CSE 100%
Installed Capacity 14.8 MW
Average Annual Energy 80 GWh
Maximum Turbine Discharge 24 m³/s
Rated Head 75 m
Turbine Type Vertical Francis x 2 Units
Offer taker EDL
Catchment Area 1,284 Km2
Annual Average Rain Fall 2,600 mm
Annual Average Discharge 53 m³/s
Reservoir Storage Capacity 0.21 M/ m3
Reservoir Surface Area 6.0 Ha
Full Supply Level 252 m a.s.l
Minimum Operating Level 249 m a.s.l
Main Dam
Type Concrete Gravity
Height 7 m
Crest Length 100 m
Crest level 252 m a.s.l
Headrace Canal
Type Open Canal
Length 1,832 m
Longitudinal Gradient 0.16
Headrace Tunnel
Type Concrete Liner
Design Discharge
Diameter 4.3m x 5.3m Horseshoe Shape
Length 1,938 m
Spillway
Type Ogee Gated
Number of Gate 5
Max Inflow peak 1970 m3/s
Design Flood Discharge
Penstock
Type Steel liner
Number of Pipe 2
Diameter 1.6 m
Length 281 m
Longitudinal Gradient 7.7%
Switchyard 115kV
Elevation 175.3 masl
Dimension 24m x 52m
Tailrace Canals
Type Concrete
Length 11.5 m
Powerhouse
Installed Capacity 14.8 MW
Number of Unit 2
Turbine Type Francis Vertical
Max Powerhouse Discharge 24 m³/s
Erection Floor Elevation 175.3 m a.s.l
115KV Transmission Line
Substation Nongbong Substation
Length 32 Km
ປະເພດສາຍສົ່ງ ສາຍສົ່ງວົງຈອນດ່ຽວ
Circuit Type 185 mm2
  • On January 13, 2011, the Water Resources and Environment Certificate was issued.
  • On January 26, 2012, the concession certificate was issued
  • On May 11, 2012 Concession Agreement signed with the government
  • On February 12, 2018, an investment license was issued
  • On 11 May 2012, Xe Nam Noy 1 Power Company Limited signed a power purchase agreement with EDL.
  • September 10, 2013. State land use license
  • On January 13, 2011, the Water Resources and Environment Certificate was issued.
  • On January 26, 2012, the concession certificate was issued.
  • On May 11, 2012 Concession Agreement signed with the government
  • On February 12, 2018, an investment license was issued

Total recipients and sub-recipients

Job division of construction work of the project contractor

  1. Main structural work and additional construction work
  • Main construction work: The construction of the building is CSG, the installation of equipment.
  • The transformers and generators are owned by Dong Fang Company.

Companies and contractors.

  • Project Owner: Xe Nam Noy 1 Hydropower Company Limited.
  • Design study by: Phongsubthavy Construction Company.
  • Monitors By: Phongsubthavy Construction Company.
  • Recipient: Phongsubthavy Construction Company hired Dong Fang Company.
  • Machinery buyer: Phongsubthavy Construction Company.
  • Manufacturer of electric machinery: Dong Fang Company.
  • Construction of 115 kw transmission line.
  • Experiments By: SAHA Trade Co., Ltd. and Electricite du Laos.
  1. In 2011 started construction of the project.
  2. In 2011 issued a certificate for water resources and environment.
  3. In 2012, the concession was issued.
  4. In 2012, a CA agreement was signed with the government.
  5. In 2013, state land use permits
  6. In 2013, the construction of the project was completed.
  7. In 2018, an investment license was issued.

Contact Us

CSE Building, Nongbon Road, Unit 8, Nongbon Village, Xaysettha District Vientiane, Lao PDR.

+856 (0) 21 417788 or 417789
headoffice@csenergy.la