PROJECT COST
$36.86M
AVERAGE ANNUAL ENERGY
80 GWh
DAM HEIGHT
7 M
CATCHMENT AREA
1,284 Km2
Installed Capacity
14.8 MW
Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam,quis nostrud exercitation ullamco laboris nisi
- ORGANIZATION CHART
- GENERAL INFORMATION
- TECHNICAL STRUCTURE
- HYDRO-ELECTRO-MECHANICAL INFORMATION
- Legislative Document
- Total recipients and sub-recipients
- Important steps of the project
Project Cost | $36.86 M |
Shareholder | CSE 100% |
Installed Capacity | 14.8 MW |
Average Annual Energy | 80 GWh |
Maximum Turbine Discharge | 24 m³/s |
Rated Head | 75 m |
Turbine Type | Vertical Francis x 2 Units |
Offer taker | EDL |
Catchment Area | 1,284 Km2 |
Annual Average Rain Fall | 2,600 mm |
Annual Average Discharge | 53 m³/s |
Reservoir Storage Capacity | 0.21 M/ m3 |
Reservoir Surface Area | 6.0 Ha |
Full Supply Level | 252 m a.s.l |
Minimum Operating Level | 249 m a.s.l |
Main Dam | |
Type | Concrete Gravity |
Height | 7 m |
Crest Length | 100 m |
Crest level | 252 m a.s.l |
Headrace Canal | |
Type | Open Canal |
Length | 1,832 m |
Longitudinal Gradient | 0.16 |
Headrace Tunnel | |
Type | Concrete Liner |
Design Discharge | – |
Diameter | 4.3m x 5.3m Horseshoe Shape |
Length | 1,938 m |
Spillway | |
Type | Ogee Gated |
Number of Gate | 5 |
Max Inflow peak | 1970 m3/s |
Design Flood Discharge | – |
Penstock | |
Type | Steel liner |
Number of Pipe | 2 |
Diameter | 1.6 m |
Length | 281 m |
Longitudinal Gradient | 7.7% |
Switchyard 115kV | |
Elevation | 175.3 masl |
Dimension | 24m x 52m |
Tailrace Canals | |
Type | Concrete |
Length | 11.5 m |
Powerhouse | |
Installed Capacity | 14.8 MW |
Number of Unit | 2 |
Turbine Type | Francis Vertical |
Max Powerhouse Discharge | 24 m³/s |
Erection Floor Elevation | 175.3 m a.s.l |
115KV Transmission Line | |
Substation | Nongbong Substation |
Length | 32 Km |
ປະເພດສາຍສົ່ງ | ສາຍສົ່ງວົງຈອນດ່ຽວ |
Circuit Type | 185 mm2 |
- On January 13, 2011, the Water Resources and Environment Certificate was issued.
- On January 26, 2012, the concession certificate was issued
- On May 11, 2012 Concession Agreement signed with the government
- On February 12, 2018, an investment license was issued
- On 11 May 2012, Xe Nam Noy 1 Power Company Limited signed a power purchase agreement with EDL.
- September 10, 2013. State land use license
- On January 13, 2011, the Water Resources and Environment Certificate was issued.
- On January 26, 2012, the concession certificate was issued.
- On May 11, 2012 Concession Agreement signed with the government
- On February 12, 2018, an investment license was issued
Total recipients and sub-recipients
Job division of construction work of the project contractor
- Main structural work and additional construction work
- Main construction work: The construction of the building is CSG, the installation of equipment.
- The transformers and generators are owned by Dong Fang Company.
Companies and contractors.
- Project Owner: Xe Nam Noy 1 Hydropower Company Limited.
- Design study by: Phongsubthavy Construction Company.
- Monitors By: Phongsubthavy Construction Company.
- Recipient: Phongsubthavy Construction Company hired Dong Fang Company.
- Machinery buyer: Phongsubthavy Construction Company.
- Manufacturer of electric machinery: Dong Fang Company.
- Construction of 115 kw transmission line.
- Experiments By: SAHA Trade Co., Ltd. and Electricite du Laos.
- In 2011 started construction of the project.
- In 2011 issued a certificate for water resources and environment.
- In 2012, the concession was issued.
- In 2012, a CA agreement was signed with the government.
- In 2013, state land use permits
- In 2013, the construction of the project was completed.
- In 2018, an investment license was issued.