Mr. Bong Bong Gayadan
- Senior Quantity Surveyor/ Project Cost Control
Date of Appointment
- March 5, 2018
Education / Training
- Registered CIVIL ENGINEER
- Construction Computer Software (C201- Construction Estimating & Valuations) Feb.2009, Dubai UAE
Work Experience
- Chaleun Sekong Energy Co.Ltd. (CSE) – Nam Kong 3 Hydropower Project, Laos PDR (54 MW) Date: March 5,2018 to Present. POSITION: SENIOR QUANTITY SURVEYOR & PROJECT COST CONTROL …
- CMC Di Ravenna – Angat Water Transmission Improvement Project – Design and Construction of Ipo to Bigte Tunnel No.4 -Date: June 19,2017 to March 3,2018. POSITION: COST CONTROL ENGINEER AND SENIOR QUANTITY SURVEYOR
- CMC Africa austral lda (CMC/CMCAA-Mozambique, Africa) Massingir Dam Bottom Outlet Rehabilitation Project. Date: April 2,2015 to June 15,2017. POSITION: COST CONTROL ENGINEER AND SENIOR QUANTITY SURVEYOR
- CMC Africa austral lda (CMC/CMCAA-Mozambique, Africa) 856km Montepuez – Ruca Road Upgrading Project. Date: March 22,2013 to March 31,2015. POSITION: COST CONTROL ENGINEER AND SENIOR QUANTITY SURVEYOR ……
- Taisei Corporation (Vietnam Branch) Noi Bai International Airport Terminal 2 Construction Project Hanoi, Vietnam. Date: April 18,2012 to February 15,2013. POSITION: CONSTRUCTION SENIOR SITE ENGINEER.………
- CMC Di Ravenna (CMC-Laos) – Theun Hinboun Hydroelectric Project (280 MW). Date: September 1,2009 to March 30,2012. POSITION: COST CONTROL ENGINEER, QUANTITY SURVEYOR AND DEPUTY QA/QC MANAGER
- Murray & Roberts Contractors (Middle East) L.L.C. – Dubai International Airport Expansion Phase 2 Project. Date June 1,2007 to August 30,2009. POSITION: QUANTITY SURVEYOR.……………
- Nishimatsu Construction Co., Inc. (NCC – Thailand). Nam Theun 2 Hydroelectric Project (1,070MW). Date: December 11,2004 to May 27,2007. POSITION: QUANTITY SURVEYOR
- Shimizu Philippine Contractors, Inc. (SPCI). Terumo Expansion and Renovation Project, Laguna Technopark, Philippines. Date: September 18,2002 to December 7,2004. POSITION: QA/QC ENGINEER
Other Directorship Positions/ Other Positions at Present
- INVOLVE IN PROJECT COST CONTROL FOR OTHER CSE PROJECT LIKE NAM PHAK, NAM EMOUN
- INVOLVE IN VARIOUS PROJECT INVESTIGATIONS LIKE NAMTHEUN 1 AND XE LA NONG HPP.