NAM KONG 3

PROJECT COST

$140.18 M

AVERAGE ANNUAL ENERGY

208 GWh

DAM HEIGHT

65 M

CATCHMENT AREA

646 Km2

Installed Capacity

54 MW

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam,quis nostrud exercitation ullamco laboris nisi

In Progress

Project Cost $140.18 Million
Shareholder CSE 100%
Installed Capacity 54 MW
Average Annual Energy 208 GWh
Maximum Turbine 60.9 m3/s
Discharge 100.7 m
Rated Head 100.7 m
Turbine Type Vertical Francis x 3 Units
Offertaker EVN
Catchment Area 646 Km2
Annual Average Rain Fall 2,576 mm
Annual Average Discharge 28.9 m3/s
Reservoir Storage Capacity 471 Million m3
Reservoir Surface Area 39 Km2
Full Supply Level 541.8 m a.s.l
Minimum Operating Level 521.0 m a.s.l
Main Dam
Type Gated concrete gravity (RCC)
Maximum height 65 m
Crest Lenght 494 m
Crest elevation 521 m a.s.l
Full Supply Level (FSL) 541,80 m a.s.l
Minimum Operation Level (MOL) 521,00 m a.s.l
Power Intake
Minimum Operation Level (MOL) 521.00 m.a.s.l
Approach channel invert level 505.25 m.a.s.l
Intake invert 506.50 m.a.s.l
Gate opening (W x H) 4.2 m x 5.3 m
Penstock
Type Steel Lined Tunnel
Number of Pipe 1
Internal diameter 4.2 m
Length 322 m
Slope 11% and 2%
Gates dimensions 11.0 m wide x 14.8 m high
Freeboard (radial gate) 0.30 m
Design Flood Discharge 5,000 m3/s (1,000-year)
Max. inflow peak 11,800 m3/s
Spillway
Type 4 radial gates
Number of Gate 1/3 Nr (one set 2x800kN and Three sets 2x3200kN
Design Flood Discharge 4860 m3/s
Headrace Tunnel
Type Concrete Lined Tunnel
Length 322 m
Internal diameter 4.2 m
Slope 11% and 2%
Tailrace Channel
Type Open Channel
Length
Switchyard 115 kV
Type AIS
Voltage level 115 kV
Powerhouse
types Vertical Francis
Number of Unit 3 Units
Installed Capacity 3 X 18 MW = 54 MW
Gross head 103.6 M
Net head (at design flow) 100.7 M
Tailrace
Connecting channel Open in rock
Riverbed 435.0 M.A.S.L.
Tail water level (TWL) 438.2 M.A.S.L.
Transmission Line
Type Double Circuit, 1×210 Mm2 ACSR
Voltage level 115 KV
Length 14.5 Km
EDL grid connection point Nam Kong 2 Switchyard

Legal Documents

  • Signed a Memorandum of Understanding (MOU) with the Government of the Lao PDR in August 2009
  • Project Development Agreement (PDA) was signed in June 2016
  • The Feasibility study of the project was approved in October 2017
  • Completed the report of Environmental and Social Impact Assessment (ESIA) in November 2017
  • Completed the Environmental and Social Management and Monitoring Plans (ESMMP) in December 2017
  • Completed the Environmental and Social Management and Monitoring Plans-construction Phase (ESMMP-CP) in December 2020
  • Completed the preparation of biomass removal plans and approved the plans for December 2021
  • Signed a power purchase agreement (PPA) with the Electricity of Vietnam (EVN) on January 04, 2020
  • Signed a concession agreement (CA) with the Government of the Lao PDR on September 2016 and completed the amendment of the concession agreement in June 2019

Contractor

  • Civil construction work

  • waterways mechanical construction works

  • electro-mechanical constructions

  • Project Owner: Chaleun sekong., co.LTD

  • Construction design company: AFRY (Thailand) Ltd

  • Consulting company: AFRY (Thailand) Ltd

  • Civil work contractor: CHINA GEZHOUBA GROUP CO., LTD (CGGC)

  • Supply and installation of waterway machinery: WHESSOE SDN BHD

  • Supply and installation of electromechanical: ANDRITZ HYDRO PRIVATE LTD

Project Phases

  1. In 2010 A Feasibility Study by JSC

  2. In 2015 Basic Design of the project by JSC

  3. In 2016, the project was handed over to Chaleun sekong., co.LTD

  4. In 2017 A Feasibility Study and Tender Design by Poyry

  5. In 2018 The construction was started by CGGC, which the consulting by Poyry

  6. In 2021, The construction by CGGC will be completed and the generator installed by Andritz.

  7. 31/10/2021 All construction of Nam Kong 3 was done.

  8. 29/11/2021 Handover Ceremony of Nam Kong 3 Hydropower Project.

Project milestones

Progress of project construction

  • Pioneering phase

  • Survey the area

  • Survey and measure water quality

  • Paving the road

  • Compensate for area damage to people

  • Start construction

10%

Overall construction phase 2019

  • CVC and RCC Concrete Mixing plant

  • Field Laboratory

  • Repair shop

  • Main dam

  • Headrace Tunnel

  • Powerhouse

30%

The Overall construction phase 2020

  • Main dam

  • Water intake

  • Headrace tunnel

  • Powerhouse

  • Switchyard

50%

The Overall construction phase 2020

  • Main dam

  • Water intake

  •  Headrace Tunnel

  • Powerhouse

  • Switchyard

70%

The Overall construction phase 2021

  • Main dam

  • water storage

  • Water intake

  • Headrace Tunnel

  • Powerhouse

  • Switchyard

  • Joint station

90%

Current construction progress

  • Main dam

  • water storage

  • Water intake

  • Headrace Tunnel

  • Powerhouse

  • Install the generator

  • Switchyard

  • Joint station

100%